Frequently asked questions.

How long does a typical remodeling project take?

The duration of a remodeling project varies based on its complexity. Kitchen and bathroom remodels typically take 3-8 weeks, while basement finishing can take 6-12 weeks.

Can you help with design ideas?

Absolutely! Our design team will work with you to create a plan that reflects your style and meets your needs. We provide 3D renderings to help you visualize the final result.

What materials do you recommend for basements?

For basements, we recommend moisture-resistant materials such as vinyl flooring, mold-resistant drywall, and insulated subflooring to prevent dampness and ensure durability.

Do you offer warranties?

Yes, we offer warranties on our workmanship and the materials we use. Specific terms depend on the project, but we ensure you’re covered for any issues that may arise post-completion.

How do you handle unexpected issues during a remodel?

Our experienced team is skilled at addressing unexpected issues efficiently. We communicate any changes or challenges promptly and work with you to find the best solutions without compromising the project’s quality or timeline.

What steps do you take to ensure project safety?

We prioritize safety by adhering to all local building codes and regulations. Our team follows strict safety protocols, and we ensure all permits are secured before starting the project.

Basement Finshing 

Questions / Answers

  • How Long Does Finishing a Basement in Utah Take?

    The time it takes to finish a basement in Utah can vary based on several factors, including the size of the basement, the complexity of the design, the availability of materials, and the efficiency of the contractor. Generally, finishing a basement can take anywhere from a few weeks to several months. Here’s a more detailed breakdown:

    1. Planning and Design 1-2 weeks

    2. Obtaining Permits 2-4 weeks (this can vary depending on local regulations)

    3. Demolition (if needed) 1-2 weeks

    4. Framing and Insulation 1-2 weeks

    5. Electrical and Plumbing 1-3 weeks

    6. Drywall Installation and Finishing 1-2 weeks

    7. Painting: 1 week

    8. Flooring Installation 1 week

    9. Finishing Touches (e trim, fixtures, final inspections)**: 1-2 weeks

    On average, a straightforward basement finishing project can take about 8-12 weeks. However, more complex projects with custom features or delays in obtaining materials or permits can extend this timeline to 3-6 months.

  • The cost of finishing a basement in Utah can vary widely based on factors such as the size of the basement, the level of finishes, and any custom features or amenities. Here are some general cost estimates:

    1. Basic Finish: $20-$35 per square foot

    - This typically includes basic drywall, carpet or vinyl flooring, minimal electrical work, and simple lighting fixtures.

    2. Mid-Range Finish: $35-$50 per square foot

    - This might include higher quality materials, such as hardwood or tile flooring, more elaborate lighting, better insulation, and additional electrical and plumbing work.

    3. High-End Finish: $50-$100+ per square foot

    - This can include custom features like built-in shelving, high-end flooring and cabinetry, additional bathrooms, a wet bar or kitchenette, home theater setups, and high-quality finishes throughout.

    **Total Costs Based on Square Footage:**

    - 500 sq ft: $10,000 - $50,000

    - 1,000 sq ft: $20,000 - $100,000

    - 1,500 sq ft: $30,000 - $150,000

    Additional Factors Affecting Cost:

    - Plumbing and Electrical Work: Adding a bathroom or extensive electrical work can significantly increase costs.

    - Permits and Inspections: Costs for permits and inspections can add to the overall budget.

    - Custom Features: Home theaters, wet bars, custom cabinetry, and other specialized features can raise costs.

    - Contractor Fees: Labor costs in Utah can vary, affecting the total cost of the project.

    - Materials: The choice of materials (e.g., flooring, countertops, fixtures) greatly influences the final price.

    To get an accurate estimate, it’s advisable to get quotes from multiple contractors and consider the specific details of your project.

  • The time it takes to remodel a bathroom in Utah can vary depending on the scope and complexity of the project. Here is a general timeline for a standard bathroom remodel:

    1. Planning and Design: 1-2 weeks

    - Includes choosing materials, fixtures, and layout.

    2. Obtaining Permits: 1-3 weeks

    - Depending on local regulations and the extent of the remodel.

    3. Demolition: 1-3 days

    - Removing old fixtures, tiles, and any necessary structural elements.

    4. Plumbing and Electrical Work: 2-5 days

    - Updating or rerouting plumbing and electrical systems as needed.

    5. Framing and Structural Changes (if any): 1-3 days

    - Includes any necessary adjustments to walls, floors, or ceilings.

    6. Drywall and Paint: 3-5 days

    - Installing new drywall, mudding, sanding, and painting.

    7. Flooring Installation: 2-4 days

    - Installing new tiles, vinyl, or other flooring materials.

    8. Installing Fixtures and Cabinets

    : 3-5 days

    - Installing new sinks, toilets, showers, tubs, and cabinetry.

    9. Tiling and Grouting: 3-7 days

    - Includes wall tiles for showers and backsplashes.

    10. Finishing Touches: 1-3 days

    - Includes installing mirrors, hardware, and any other final details.

    **Total Time**: 2-4 weeks

    This timeline assumes a relatively straightforward remodel with no major structural changes or unforeseen complications. More extensive remodels, such as moving plumbing or electrical lines or dealing with structural issues, can take longer, possibly extending the timeline to 4-8 weeks.